Illustrative deliverable

An example private deployment readiness assessment

See how an assessment can turn private AI requirements into a dependency map, responsibility matrix, cost assumptions, and pilot acceptance criteria.

Illustrative example. This is a fictional planning scenario, not a customer case study, a tested architecture, or a completed Tenantplane deployment.

The requirement

A B2B document-assistant vendor has a customer requesting deployment inside its cloud account. The application currently calls an external model API. The customer asks that inference, document processing, retrieval, and associated logs stay inside the agreed environment.

The assessment covers one application and one target account. It does not assume that substituting an open-weight model will preserve task quality. That question requires representative evaluation in a pilot.

Architecture and dependencies

Component Proposed location Decision still needed
Application API Customer environment Supported installation target and ingress
Model inference Customer environment Model license, quality, runtime, GPU availability
Embedding and retrieval Customer environment Embedding model, index storage, document permissions
Identity Customer identity provider Protocol, service accounts, role mapping
Model artifacts Approved local registry/storage Distribution rights, transfer process, version pinning
Logs and metrics Agreed customer tools Sensitive-field redaction, retention, diagnostic export
Updates Versioned release artifacts Import, validation, approval, rollback

Every network dependency needs a decision. Model downloads, certificate validation, identity, license checks, package registries, and error reporting can all affect the boundary. An assessment should expose unresolved dependencies rather than silently assume internet access.

Responsibility matrix

This is a proposed division to review with the actual customer and software vendor.

Work Proposed accountable owner Required input
Provision compute, storage, and networking Customer infrastructure owner Resource and access specification
Package the application and model runtime Software vendor Versioned application and supported dependency list
Approve access and outbound paths Customer security owner Dependency map and account permissions
Run installation and acceptance checks Named implementation owner Approved environment, workload, acceptance plan
Operate backups and incident response Customer or separately contracted operator Runbook, escalation path, service expectations
Approve release updates Agreed customer change owner Release notes, compatibility tests, recovery steps

For each row, the final engagement records a named owner. “The team” is not specific enough for a recovery or access request.

Risks that need a pilot decision

  1. Model quality: the open-weight candidate may not meet the application’s existing quality baseline. Compare on a permissioned representative task set.
  2. Document authorization: login alone does not establish which documents an individual can retrieve. Test authorized and unauthorized cases.
  3. Capacity: concurrency and context length may require different hardware from a developer’s proof of concept. Benchmark the actual workload before committing to a throughput target.
  4. Dependencies: an external service may have no suitable replacement within the customer’s restrictions. Resolve or explicitly exclude it.
  5. Recovery: restoring a database and rolling back an application image may have different compatibility requirements. Test the complete recovery path.

Cost assumptions

The cost sheet separates implementation labor, infrastructure, licensing, ongoing operation, and recurring compatibility work. It identifies which party pays for each category and marks every unverified rate or capacity assumption.

An estimate without a workload profile is a planning range. It becomes a deployment budget only after hardware, provider pricing, runtime behavior, and the operating agreement have been validated. See the private deployment cost guide for a worked hypothetical example.

Pilot acceptance criteria

Each check should record the method, observed result, supporting artifact, and owner.

Check Proposed evidence
Reproducible installation Clean-environment install log with exact versions
Application behavior Results against an agreed representative task set
Access controls Positive and negative authorization test results
Network boundary Approved egress inventory and test observations
Update and recovery Upgrade plus recovery rehearsal, including state
Operator handover Customer operator completes a documented routine task

The pilot scope includes one target environment. Additional clouds, versions, models, or hardware configurations expand the validation work and need an explicit decision.

What the decision should say

The written conclusion is one of: proceed with the defined pilot, resolve specific blockers first, or do not proceed under the current constraints. The value of an assessment is a grounded decision; a recommendation to deploy at any cost is not useful.

This fictional example illustrates the kinds of findings a readiness sprint can contain. It is not a client case study, an executed assessment, or a guarantee of these conclusions for another application. Review the proposed $2,500 readiness sprint and the separate private workflow implementation.

Published by Tenantplane, a U.S.-based private AI deployment consultancy. These are planning considerations; your deployment scope and acceptance checks depend on the actual application and customer environment.